How can a contractor claim release of retention money?

A contractor's entitlement to release of retention money under a FIDIC contract is determined by the applicable retention clause, the stage of completion, required certificates and any lawful deductions. Sub-Clause 14.9 in FIDIC's 1999 and 2017 construction forms addresses retention, subject to edition and amendments. Retention is not necessarily a general fund the employer may hold indefinitely to secure every possible disagreement. Equally, the Taking-Over Certificate does not automatically release the entire sum in every form. A proper claim requires examination of the particular contract and payment chronology.

What retention money represents

Retention is typically a portion deducted from interim payments up to a contractual cap to secure defined performance obligations.

It should be distinguished from a performance guarantee, advance payment guarantee and defects liability. The legal mechanisms differ even if all relate to contractor performance.

Establish the executed terms

Obtain Contract Data, Particular Conditions, interim payment certificates and retention calculation schedule.

A standard form may be amended to substitute a retention guarantee or alter release dates. The contract's actual wording prevails over an assumption based on an unamended FIDIC manual.

The applicable FIDIC clause

Sub-Clause 14.9 is the usual retention release provision in relevant FIDIC forms.

The exact procedure and split can differ across editions or bespoke terms. Counsel should read the operative contract rather than claim that every FIDIC contract necessarily releases fifty percent at the same time.

Calculate retention withheld

Review every interim payment statement and certificate, recording gross amount, retention deduction, tax, advance recovery and net payment.

A contractor should separately identify amounts wrongly withheld as retention rather than other contractual deductions. The cumulative total must be compared with the agreed cap.

Taking-Over Certificate

A Taking-Over Certificate may trigger entitlement to release a prescribed first portion of retention, depending on the form.

The certificate should identify the works or section taken over and relevant date. Employer use of a facility may raise factual issues but is not always a substitute for the prescribed certificate.

Sections and partial taking-over

A project may be divided into sections with separate milestones. Retention release can depend on taking-over of a section according to contract provisions.

An employer should not automatically withhold all retention because an unrelated section remains incomplete if the contract provides proportionate release. Actual wording and valuation matter.

Defects Notification Period

Retention can support obligations during the prescribed defects period. The contractor should identify the start, duration, extensions and rectification history.

A pending minor defect may affect a defined amount, but the employer should not assume an unlimited right to retain the entire fund indefinitely without contractual basis.

Performance Certificate

The Performance Certificate may be a later milestone for release of remaining retention under the contract.

The contractor should request the certificate when the legal conditions are met and document any failure to issue it. The absence of a certificate can create a separate claim or dispute but does not always determine the merits automatically.

Defect notices and disputed work

An employer may identify outstanding defects and require correction. Determine whether the alleged items are actual defects within the contractor's responsibility.

A generic statement that "work quality is unsatisfactory" may not justify every deduction. Detailed defect lists, inspection records and contract specifications should be examined.

Other alleged claims

The employer may claim delay damages, replacement costs or other amounts. Each requires its own legal and contractual basis.

Retention should not be treated as unlimited collateral for every unassessed allegation, particularly where the contract prescribes separate claims and determination procedures.

Certified amount versus disputed debt

An amount recognised in an interim certificate may become due under Clause 14 according to its terms.

A dispute concerning an employer counterclaim does not automatically allow withholding of every undisputed certified payment. The parties should reconcile sums separately and identify rights of setoff or deduction.

Statement at completion

Contractors may be required to submit a Statement at Completion or related documentation identifying outstanding amounts.

The retention claim should be included and supported by certificates and payment schedules. Missing a contractual submission step can delay processing even where retention was actually deducted.

Final statement and discharge

Final payment procedures may involve a statement, discharge and Final Payment Certificate. The contractor should understand the effect of signing a final discharge.

An unconditional document claiming no outstanding entitlement can create difficulties if retention or variations remain disputed. Reservations should comply with contractual requirements.

Retention guarantee substitution

Some contracts allow the contractor to substitute a retention bond or guarantee for withheld cash.

This can improve cash flow but depends on acceptable security form, expiry and employer approval. A bank guarantee may have its own independent demand obligations.

Interest on late release

Delayed payment provisions such as Sub-Clause 14.8 may apply where payment becomes due and is delayed, subject to contract and circumstances.

The contractor should calculate financing costs using the actual agreed formula. Do not invent a standard interest rate or assume all sums attract the same treatment.

Design and approval delays

Employer-caused design delays can prolong completion and the retention release timetable. The contractor may have associated EOT or cost claims.

Such matters must be proved under the governing clauses. A delayed project does not automatically entitle immediate release of all security without considering stage and defects obligations.

A completed infrastructure project example

A city technology system receives a Taking-Over Certificate, enters a defects period and remains operational. The employer continues withholding substantial retention while demanding unrelated documents.

The contractor should identify the contractual release milestone, outstanding defects and any Performance Certificate entitlement. A payment claim can be advanced through the determination and dispute process.

A partial works example

A contractor completes one section of a road project while remaining sections continue. The employer withholds all retention until completion of the entire contract.

The contractor should examine whether the contract grants proportionate release for sections. The legal result depends on contract drafting and the actual taking-over record.

Notice and claims procedure

If the employer refuses release, send a formal statement identifying the amount, provision, milestone and supporting certificates.

Consider Sub-Clause 20.2 claims procedures where applicable, followed by the relevant determination and DAAB route. Preserve notices to avoid time-bar disputes.

Audit of payment records

Prepare a single retention ledger identifying each invoice, deduction, cap, certificate and release amount.

This should distinguish retention from VAT, withholding tax, advance recovery and other deductions. A reconciled figure is essential before claiming interest or damages.

Opinion and recommended course

A contractor can claim release of retention when contractual milestones and conditions are satisfied. Under relevant FIDIC forms, examine Sub-Clause 14.9, Taking-Over and Performance Certificates and any lawful defects-related deduction. Provide an exact ledger and pursue determination and dispute resolution rather than rely on informal requests for cash.

Principal authorities: FIDIC construction forms, Sub-Clauses 14.8–14.9, Clauses 10–11 and relevant payment and claims provisions; Particular Conditions; Contract Act, 1872; governing arbitration and public procurement law.

LEGISLATION, SOURCES & CASE LAW

Contract Act, 1872 ↗

Consult the current enactment and any subsequent amendments and reported judgments for the relevant jurisdiction.
Useful? Join the discussionLegal information, not client-specific advice