Conditions Precedent in Project Finance: Why Documents Delay Drawdown

A project can reach financial close in principle yet be unable to draw funds because a consent, security document or completion certificate is missing. Conditions precedent control the lender's exposure before disbursement, but poor drafting can turn them into an indefinite financing obstacle.

Each condition needs a legitimate risk purpose

Conditions precedent may require corporate approvals, permits, insurance, legal opinions, security perfection, equity contributions and execution of project contracts. The list should correspond to risks that must be resolved before funds are advanced. A requirement for 'all satisfactory documents' leaves unnecessary uncertainty unless standards and responsible decision-makers are identified. The borrower should review the list against the project implementation timetable before signing, particularly where a permit can only be obtained after construction expenditure. Impossible conditions should be restructured, not left for an assumed later waiver.

Authority and documentary consistency matter

Board resolutions, shareholder approvals, constitutional documents and financing undertakings should describe the same borrowing and security package. The project agreements must identify the right entities and assets. A legal opinion cannot correct an unexecuted document or an authority that was never granted. Where property security or assignments require registration, evidence of completion may be essential to enforceability. The parties should allocate responsibility for each filing and identify what constitutes acceptable proof of completion rather than rely on general assurances.

Equity and debt drawdown should be coordinated

Lenders may require sponsors to inject their contribution before or alongside debt. The documentation should state the amount, form and timing of equity, and whether shareholder loans count toward the commitment. Borrowers need certainty about whether a proposed early expenditure qualifies as eligible project cost. A mismatch between the construction payment schedule and drawdown conditions can create claims from contractors even when the facility is otherwise approved. Funding plans should account for the time required to satisfy each precondition and cure documentary defects.

Waivers and repeated representations should be clear

A lender may waive a condition for an initial drawdown while reserving it for later advances. The legal effect depends on the waiver's terms and whether related representations remain true. Conditions subsequent can sometimes permit timely funding without compromising an important perfection step, but only when the risk and deadline are responsibly managed. Borrowers should not assume that acceptance of one incomplete document creates a standing waiver. A live conditions checklist with owners, evidence and status should be maintained through financial close and the drawdown period.

Drawdown readiness is a project deliverable

Conditions precedent should serve the credit decision, not become an unmanaged list of potential vetoes. Their effectiveness depends on clarity, realistic timing and a disciplined evidence trail. Project teams should resolve these matters before contractors and suppliers are relying on funds not yet legally available.

NINETY TWO CHAMBERS / LEGAL ADVISORY

When the issue arises in practice.

Our advice begins with the governing documents, the legal position and the decision that needs to be made.

DISCUSS THIS MATTER

This publication is for general information and does not constitute legal advice on any particular matter.