Whether a Dispute Avoidance/Adjudication Board (DAAB) must be constituted before commencing arbitration depends on the exact FIDIC edition and signed dispute resolution clause. Under the FIDIC 2017 Silver Book, the general framework provides for a DAAB under Sub-Clauses 21.1–21.5, but Sub-Clause 21.8 specifically addresses the situation where no DAAB is in place or is being constituted. In that defined situation the general conditions allow direct arbitration under Sub-Clause 21.6 without completing the ordinary board-decision and amicable-settlement stages. Particular Conditions and amendments must nevertheless be examined before relying on that exception.
The importance of the signed edition
FIDIC Red, Yellow and Silver Books exist in different editions. An arbitration opinion should identify whether the parties adopted the 1999 or 2017 conditions, which amendments apply and the content of Particular Conditions. A clause numbered 20.8 under an earlier form cannot simply be quoted as though it were Sub-Clause 21.8 in the 2017 form. Dispute procedures are contractual prerequisites, so accurate wording matters.
The purpose of the DAAB
The DAAB is intended to assist in dispute avoidance and provide an interim binding determination under the agreed mechanism. The board can be a single member or three members depending on the contract. Its role differs from an arbitral tribunal finally deciding the dispute. The system aims to resolve technical and commercial issues during project performance without immediately resorting to full arbitration.
Constitution under Sub-Clause 21.1
FIDIC 2017 provides for constitution of the DAAB through agreed appointment arrangements. The Particular Conditions may designate a standing board or specify appointment dates. The parties should examine whether the obligation arose at contract signing, commencement or another defined event. A party's failure to take part in appointment may itself be relevant to contractual compliance. The existence of a named adjudicator is distinct from a board legally constituted and able to accept referrals.
Failure to appoint under Sub-Clause 21.2
The conditions include an appointment mechanism where the parties cannot agree on a board member. The precise appointing authority and steps should be read from the executed text. A party should not automatically invoke the no-board exception merely because it has not personally nominated anyone. If a board is actively being constituted through the prescribed procedure, that fact may affect the applicability of Sub-Clause 21.8.
Referral and DAAB decision
Where a duly constituted DAAB exists and the dispute clause requires referral, a party may need to submit the dispute for decision before arbitration. The time limits and effect of decisions should be followed strictly. An adjudication determination may be binding pending final resolution even where challenged through the required notice process. A party should not regard an adverse DAAB decision as meaningless because an arbitral tribunal might later reach a different conclusion.
Notice of dissatisfaction
Relevant FIDIC clauses can require a notice of dissatisfaction to preserve rights to arbitration following a board decision. The notice should identify the decision and grounds within the contractual time period. Missing an operative time limit can affect finality or enforceability. The parties should verify whether a notice is required for the actual outcome rather than submit an informal complaint to project management and assume it suffices.
Amicable settlement
An amicable-settlement stage can precede arbitration under the normal mechanism. The relevant clause and waiting period should be read as contractual requirements. However, the 2017 Silver Book's no-DAAB provision expressly excludes the ordinary Sub-Clause 21.4 and 21.5 stages in its stated circumstances. A lawyer should not demand the ordinary amicable waiting period if the properly interpreted exception disapplies it.
Sub-Clause 21.8: no DAAB in place
The clause deals with a dispute where no DAAB exists or is being constituted, whether because its appointment expired or otherwise. On its terms, Sub-Clause 21.4 concerning a DAAB decision and Sub-Clause 21.5 concerning amicable settlement do not apply, and either party may refer the dispute directly to arbitration under Sub-Clause 21.6. The availability of that route depends on the actual facts and any Particular Conditions changing the provision.
Nonconstitution caused by a party
If one party deliberately obstructs board formation, the contractual consequences should be examined carefully. It may be relevant whether the appointing-authority mechanism was available and used, and whether the board is technically still "being constituted." A party should not engineer the failure of a mandatory preliminary step and then assume arbitration is automatically unaffected. However, the unamended wording of Sub-Clause 21.8 may still provide an operative route in appropriate circumstances. The exact interpretation should be supported by evidence.
Contract amendments and bespoke clauses
Public contracts frequently revise FIDIC arbitration provisions. The Particular Conditions may delete or modify Sub-Clause 21.8, substitute another board or impose institution-specific notice requirements. A standard-form commentary cannot resolve an amended dispute mechanism. Obtain the executed General and Particular Conditions, relevant appendices, amendments and any later agreement. An arbitration notice should cite the actual operative clause rather than an assumed FIDIC model.
Dispute crystallisation
A disagreement becomes a dispute when the relevant contractual conditions for dispute have been met; not every unanswered invoice immediately amounts to an arbitrable dispute in every contract. Examine prior claims, determinations, employer responses and notices. For an unpaid construction claim, identify whether a required claim or determination process was completed or has failed to operate. Establishing the amount and nature of the dispute supports the jurisdictional case.
Jurisdiction and admissibility
An arbitral tribunal may be asked whether a failure to use the DAAB affects its jurisdiction or the admissibility of claims. The outcome depends on contract, governing law and procedural posture. Counsel should distinguish lack of arbitration agreement from noncompliance with a pre-arbitration condition. The legal analysis should not simply assert that a missing DAAB makes all arbitration invalid or that every procedural step is optional.
Pakistani arbitration framework
The Arbitration Act, 1940 remains relevant to domestic arbitration, while foreign arbitration agreements and enforcement can engage the Recognition and Enforcement (Arbitration Agreements and Foreign Arbitral Awards) Act, 2011 and applicable treaties. The seat of arbitration and governing procedural rules are crucial. A FIDIC clause choosing ICC arbitration seated outside Pakistan can involve a different legal route from domestic ad hoc proceedings. Local court intervention and enforcement must be assessed separately.
Employer and contractor consent
A party may propose that both sides waive the DAAB and proceed directly to arbitration. A valid written agreement can clarify procedure, subject to law. Silence should not automatically be treated as an agreed waiver. The parties should preserve meeting minutes and express correspondence. Where both parties actively pursued appointing the DAAB, the status of that process should be accurately disclosed to any tribunal.
A delayed-payment example
A contractor claims substantial certified unpaid amounts under a 2017 Silver Book project. No DAAB was ever appointed and neither party is actively constituting one. The contractor may examine Sub-Clause 21.8 and initiate arbitration directly if the executed clause retains the standard exception and the dispute has crystallised. It should present the appointment history and contractual text rather than simply state that a DAAB is inconvenient.
An already-constituted board example
A standing DAAB has been validly appointed, and the contractor bypasses it to commence arbitration over delay damages. Unless a distinct contractual exception or lawful waiver applies, the employer may object that the agreed adjudication route was not followed. The contractor must examine the consequences, any available referral and whether the issue is one of jurisdiction or admissibility. The no-board exception cannot be invoked where an operative board actually exists.
Drafting the arbitration notice
Identify the parties, contract, operative arbitration agreement, governing law, relevant dispute and amount or relief claimed. If relying on Sub-Clause 21.8, state why no DAAB is in place or being constituted and how that exception applies. Attach the essential contract and appointment correspondence. Preserve all contractual claim notices and supporting records to avoid separate substantive time-bar disputes.
Opinion and recommended course
A DAAB is ordinarily part of the FIDIC 2017 dispute mechanism, but it is not an absolute prerequisite in every case. Under unamended Sub-Clause 21.8, direct arbitration is permitted where no DAAB is in place or being constituted. Verify edition, amendments, board appointment status, dispute maturity and arbitral seat before filing or objecting to arbitration.
Principal authorities: Signed FIDIC 2017 Silver Book, Sub-Clauses 21.1–21.8, especially 21.8; Arbitration Act, 1940; Recognition and Enforcement (Arbitration Agreements and Foreign Arbitral Awards) Act, 2011; relevant arbitral rules and Particular Conditions.
Discussion
Start a thoughtful discussion. Published comments are reviewed by our editorial team.