Mandatory Pre-Arbitration Steps: Negotiation, Dispute Boards and Time Limits

Commercial and construction contracts often require negotiation, an engineer's determination, mediation or a dispute board before arbitration. When the relationship deteriorates, parties may be tempted to skip those steps. The legal consequence depends on the wording and purpose of the agreed procedure.

Not every escalation clause creates the same obligation

A statement that parties 'may attempt amicable settlement' differs from a clause providing a defined notice, meeting and waiting period before arbitration can be commenced. The relevant language should identify who must act, what event triggers the stage and how completion or failure is recorded. If a precondition is ambiguous, the dispute may shift from the merits to whether the tribunal can hear it at all. A drafting exercise should distinguish aspirational cooperation from an enforceable procedural mechanism and should not prescribe steps that one party can obstruct indefinitely.

Contract administration and dispute resolution may overlap

FIDIC-based projects can involve notices of claim, determinations, notices of dissatisfaction and dispute boards. Those stages serve different functions. A party should identify whether a claim has been properly submitted, whether a determination is binding pending challenge and whether a notice preserving the right to escalate was served on time. An employer's failure to make a determination may raise particular contractual consequences, but it does not automatically permit the contractor to disregard every subsequent procedural requirement. The executed form and Particular Conditions remain central.

Time limits and limitation must be tracked separately

An agreed period for issuing a notice or commencing a dispute stage can operate alongside statutory limitation periods. Completing mediation late does not necessarily extend statutory time unless the governing law or agreement validly provides the relevant effect. Counsel should maintain a chronology of contractual and statutory deadlines, and consider protective steps where a stage is unresolved. The content of a reservation-of-rights letter is not always a substitute for a prescribed formal notice. A party should not allow continuing commercial discussions to obscure the date by which proceedings must lawfully be commenced.

Design a mechanism that cannot be stalled

The clause should specify a representative authorised to negotiate, a fixed period for the step, an appointment method for neutrals and what follows if a party refuses to participate. It may also permit urgent interim relief without first completing an extended sequence. A workable process can resolve technical disputes early and reduce arbitration costs. An unworkable clause may simply give a defaulting party another opportunity to delay enforcement. The commercial context, likely dispute size and need for continued project performance should determine the length and form of escalation.

Escalation should lead to a binding decision

Before commencing arbitration, the claimant should prepare a procedural compliance schedule alongside the substantive claim. The respondent should identify any genuine omitted step without assuming that every imperfect negotiation deprives the tribunal of jurisdiction. Precise escalation clauses benefit both sides because they make the pathway to a binding decision predictable.

NINETY TWO CHAMBERS / LEGAL ADVISORY

When the issue arises in practice.

Our advice begins with the governing documents, the legal position and the decision that needs to be made.